A capital project at Milford Mill Trail includes repairs and upgrades to the trail, boardwalk and benches. During construction, the scope expanded to include a realigning of the trail and additional stream bank restoration because of erosion. Stream restrictions prevent work from taking place until June 1. These restrictions are due to the typical rainfall and the softness of the soil, which make the area more susceptible to erosion.
The park is expected to be ready to open in July 2025.